Where Your Marana Neighborhood Falls in the I-10 Interchange Schedule

November 19, 2026

In 2024, a count location near Moore Road and Interstate 10 averaged 1,446 vehicles a day. Locations around the Cortaro Road interchange averaged more than 20,000 a day over the same year, according to Pima Association of Governments figures that AZPM reported in March. Under the regional transportation plan voters approved this year, Moore Road gets its new interchange first and Cortaro gets its rebuild last.

If you're comparing homes in Marana, that order matters more than any single project's ribbon-cutting date. The rebuild schedule runs years into the future. The commute you'll have on the day you move in depends mostly on something you can already check: whether your nearest exit crosses the Union Pacific tracks at street level, or goes over or under them.

The order on paper

Pima County voters passed Propositions 418 and 419 in the March 10, 2026 special election. That extended the Regional Transportation Authority's half-cent sales tax to pay for the RTA Next plan. Proposition 418 passed with 60.4% of the countywide vote, and Marana voters supported it at 64.9%. The plan groups its projects into five-year periods measured in fiscal years. The first period covers fiscal years 2027 through 2031, and the third covers 2037 through 2041. On October 6, the Town of Marana confirmed where its interchanges fall.

I-10 exit 2024 average daily traffic near the exit RTA Next work Period Total budget
Moore Road 1,446 New interchange, road separated from the railroad, more lanes on Moore Road FY 2027–2031 $120 million
Tangerine Road 10,771 Rebuilt interchange raised over I-10 and the railroad, Tangerine widened FY 2032–2036 $185 million
Cortaro Road More than 20,000 Rebuilt interchange raised over I-10 and the railroad, Cortaro and I-10 widened FY 2037–2041 $240.3 million

Most of each budget comes from outside the RTA. At Cortaro, the RTA share is $20.3 million of the $240.3 million total. At Moore Road, it's $30 million of $120 million. The Pima Association of Governments project list updated October 16 shows the Moore Road interchange with Marana as sponsor and design-phase funding attached.

Why Moore Road goes first

The railroad explains much of this. Marana's Transportation Master Plan says the Union Pacific line follows the I-10 corridor through town with 16 trains during the day and 16 at night. The line has six street crossings at grade, and the plan names Cortaro Farms Road and Tangerine Road as the high-traffic roads where those crossings can cause delays. Rebuilding either interchange means building a bridge over both the freeway and the tracks. During that work, the drivers who use it need somewhere else to get on I-10.

Marana Town Manager Terry Rozema told AZPM that the Town decided in spring 2025 that Moore Road had to come before Tangerine. Without it, construction would push all of northern Marana's traffic onto the single interchange at Marana Road. "Moore Road becomes probably the most important trigger that needs to be pulled so that we can do the rest of them," he said in AZPM's report.

The same report describes how the project got into the plan. The Town's 2024 transportation plan listed a Moore Road interchange as a mid-term goal for the 2030s. It moved up after Tucson asked to drop a State Route 210 extension from RTA Next in late July 2025, and Moore Road first appeared in drafts less than two weeks before the plan was adopted. Marana's master plan also calls for extending Moore Road to Adonis Road. San Lucas Community Park is on that road, at 14040 N. Adonis Road in North Marana.

The project order is set by construction sequencing, not by traffic volume. Moore Road is the detour that makes the Tangerine rebuild possible, and Tangerine has to be finished before the plan reaches Cortaro.

Continental Ranch already has a way around the tracks

Continental Ranch is the case where the schedule looks worst and the daily drive can work out better than it looks. A local history describes it as Marana's first master-planned community, west of I-10 and north of Cortaro Road, with homes going up by 1989. Cortaro is the exit with the heaviest traffic and the longest wait for a rail bridge.

The Town's 2019 map atlas lists the Twin Peaks, Ina and Orange Grove crossings as grade-separated from the railroad. The Twin Peaks roadway and interchange, from Silverbell Road to I-10, was a project in the RTA's first plan and was finished in 2010. This fall, the Town marked the end of its Twin Peaks Road and Rattlesnake Pass improvements, which added road widening, drainage work, a multi-use path and a rattlesnake sculpture.

South of Cortaro, the freeway itself is newer. ADOT finished rebuilding I-10 between Ina and Ruthrauff roads in May 2026. Construction began in February 2023 and widened nearly four miles of freeway from three lanes to four in each direction. ADOT put the total at $171 million.

Cortaro also has work happening before 2037. ADOT is running an I-10 Marana to Cortaro Roads Traffic Circulation Study to find cost-effective ways to cut delays at Marana Road, Cortaro Road and the intersections between them. Its posted schedule lists a draft preferred alternative and a community-wide comment survey for fall 2026, then work beginning on a draft report in spring 2027 and on a final report with early design plans in summer 2027.

For a house in Continental Ranch, a practical question is how close it sits to Twin Peaks Road compared with Cortaro. A home that reaches I-10 through Twin Peaks uses a crossing that already clears the tracks. Daily life in the neighborhood also centers on places away from the freeway. The Continental Ranch Community Association's Community Center and pool are at 8881 N. Coachline Blvd., with a Town park across the street.

North Marana is living through its interim phase now

Up north, the near future means construction. The Town lists Gladden Farms Community Park at 12205 N. Tangerine Farms Road in North Marana, and Tangerine Road is the main route between that area and I-10. The full grade-separated Tangerine interchange is in the second RTA Next period. Interim work is underway in the meantime.

The Town's Tangerine Road and Interchange Improvements page lists the work in phases:

  • Phase 1, the westbound off-ramp work with a new dedicated turn lane and more vehicle storage, is complete.
  • Eastbound intersection work with new signals and realigned ramps was scheduled for March and April 2026.
  • Underpass abutment work runs from mid-May 2026 to March 2027.
  • The railroad crossing improvements and the full grade-separated interchange have no construction schedule yet.

The Town also posted a printable "Bingo Bonanza" card for drivers waiting in what it calls the Tangerine Squeeze.

East of the freeway, the Tangerine Road phase from Dove Mountain Boulevard to I-10 was completed in April 2026. RTA Next funds the final widening phase from Marana Tech Park Drive to Dove Mountain Boulevard as a four-lane parkway with bike lanes, at $14.2 million total.

For a buyer in Gladden Farms, San Lucas or nearby newer communities, the schedule runs in the opposite direction from Continental Ranch. North Marana's Moore Road interchange is in the plan's first period, and it is the first new freeway connection planned for this area. The tradeoff is that the north side's existing Tangerine exit is the one being rebuilt over the next several years, and its railroad crossing work hasn't been scheduled. Our earlier guide to new-home communities in Marana covers the building side of those neighborhoods.

What the regional numbers can't show you

The Multiple Listing Service of Southern Arizona's October 2026 report puts Tucson's Northwest region at 191 sales, a $460,000 median sale price, $252 per square foot and 27 median days on market for the month. Those figures cover a wide area. Continental Ranch and the newest subdivisions north of Tangerine are averaged together, so a median can't tell you which homes sit near a crossing that clears the railroad.

The same street can feel very different depending on which exit you take. Before you commit to a house, drive from it to I-10 at the hour you'd actually commute, once through each nearby exit. With 32 trains a day on the line through town, one test drive may or may not catch a train. Two or three trips at the same hour will give you a better read on a street-level crossing. If you're weighing a longer commute toward Phoenix, our post on the Phoenix-Tucson corridor covers that drive.

FAQ

Which RTA Next period is the Moore Road interchange in? Moore Road is in the first period, fiscal years 2027 through 2031. Tangerine is in the second and Cortaro in the third.

Is anything happening at Cortaro before the 2037–2041 period? ADOT's Marana to Cortaro traffic study is looking for cost-effective ways to reduce congestion between Marana Road and Cortaro Road. ADOT plans to begin the final report and early design plans in summer 2027.

Which Marana-area exits already cross the railroad on a bridge or underpass? The Town's 2019 atlas lists Twin Peaks, Ina and Orange Grove as grade-separated crossings. Cortaro and Tangerine are among the crossings planned for future separation.

If you're comparing homes on either side of Tangerine, or thinking about selling in Continental Ranch and buying farther north, I am Home Arizona Group can help you map each address to its exit and drive the routes with you, in English or Spanish. If you already own in Marana, start with a free home valuation, and we'll walk you through what nearby sales show about your part of town.